- Joined
- Dec 15, 2023
- Messages
- 52
about 15-20% done was demolished before he started work.
Note: This feature may not be available in some browsers.
Your honor, the defendant still is represented by Prestige Law Firm. Just because blaze quit doesn’t mean Prestige no longer represents their client.@Unseatedduke1 my lawyer is quitting dc, requested extension to get a new one?
You have 42 hours to either find a new lawyer or request a Public Defender.@Unseatedduke1 my lawyer is quitting dc, requested extension to get a new one?
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONThe would demolish the plot for 5k in the day then requested 15k
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONTIN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
QUESTIONS FOR THE WITNESSES
1) [To NotPhunky] What were the terms of NotBender’s employment?
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
OBJECTION
PERJURY
1) In response to the question, “In reference to the agreements shown in P-001 and P-002, could both of you please state the terms you believed to be agreed upon (the final agreement)?” The witness answered, “the agreement was that i paid the user 15k for their work.” Now the same witness is stating, “he would demolish the plot for 5k in the day then requested 15k. It is evident that the witness is now twisting his answers to be able to fit the defense’s narrative, and based on P-001 and P-002 the ladder answer has been perjured.
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
OBJECTION
ASKED AND ANSWERED
1) The same question that has been asked by the plaintiff has been asked by the defense, they both ask for the agreed upon terms of the plaintiff’s employment, only worded differently.
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONTBecause they couldn't be on today when we agreed only today.
@Hypegamer231 Please answer the question in the next 24 hours.IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
QUESTIONS FOR THE WITNESSES
1) [To HypeGamer231] Did you make any attempts to resolve this dispute outside of court before filing the lawsuit?
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONTOverruled. The omission of a time limit does not constitute providing false information. If there is another aspect of your objection that I have misunderstood, please clarify.
No, and I apologize for the late responseIN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
QUESTIONS FOR THE WITNESSES
1) [To HypeGamer231] Did you make any attempts to resolve this dispute outside of court before filing the lawsuit?
It does indeed confuse me; please provide further clarity.IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
MOTION TO RECONSIDER
Your honor, I would like to point out point two. Point two shows that even if there was a time limit, the answer is simply false. The plaintiff was on that day, as the witness admitted that HypeGamer231 had made 15-20% progress on the demolition. If there was only one day (June 1st) for demolition and 15-20% of demolition progress had been made by the plaintiff, then the plaintiff was on that day (June 1st) to have been able to make that progress. The same witness even admitted that the plaintiff had begun work on June 1st. I will be able to provide further clarification if this explanation confuses you, your honor.
The witness confirmed that HypeGamer231 had made 15-20% progress on the demolition. If the demolition was supposed to be completed in one day (June 1st) and 15-20% progress was made, then the plaintiff must have been working on June 1st to achieve that progress. Therefore the witness has lied when they stated "they couldn't be on today."It does indeed confuse me; please provide further clarity.
Sustained.The witness confirmed that HypeGamer231 had made 15-20% progress on the demolition. If the demolition was supposed to be completed in one day (June 1st) and 15-20% progress was made, then the plaintiff must have been working on June 1st to achieve that progress. Therefore the witness has lied when they stated "they couldn't be on today."
TLDR, the 15-20% didn't demolish itself
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONTIN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
CLOSING ARGUMENT
Your honor,
May it please the court,
My client hired the plaintiff to demolish a building on C563 for $15,000. However after the plaintiff logged off, only 15%-20% of the building had been demolished. The plaintiff leaving during demolition had never been communicated within the agreement in the evidence provided.
Furthermore, my client attempted to pay the plaintiff however their bank never responded to their requests for a loan to pay for the plaintiff’s services.
Additionally, the plaintiff never attempted to get paid for their work or settle the dispute, and instead immediately filed a lawsuit.
As we can see, my client has tried their best to pay the plaintiff however due to reasons out of their control they haven’t been able to. So the question lies, should my client have to pay over double of the agreed amount for services that were never fully rendered? The plaintiff’s decision to leave the job incomplete and immediately pursue legal action without attempting to resolve the matter amicably is indicative of bad faith, especially as my client was not only willing to put attempted to pay the plaintiff for their work.
Thank you.
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
VERDICT
HypeGamer231 V. NotPhunky [2024] FCR 81
I. PLAINTIFFS POSITION
1. The plaintiff and defendant entered into an original agreement for the plaintiff to demolish the structure on c563 for $5,000.
2. The plaintiff and defendant then negotiated this price to $15,000 for the same amount of work.
3. The defendant removed the plaintiff from the plot, preventing him from making progress.
4. The defendant hasn’t paid the plaintiff for their work, nor the work that the plaintiff was unable to do due to the defendant’s deliberate actions.
II. DEFENDANT'S POSITION
1. The Defendant only removed the Plaintiff from the plot when they had been inactive and needed to find someone else who would be willing to complete the job. If anyone breached the agreement, it would be the Plaintiff.
2. The Defendant was truly willing to pay the Plaintiff for their work; however, the Plaintiff completed an insignificant amount of the demolition and then became inactive. The Defendant simply wanted their building demolished, and the Plaintiff's actions made it evident that they would be unable to do that. Therefore, the Defendant was right to find another worker to demolish the building.
III. THE COURT OPINION