Towloo
Citizen
Representative
Homeland Security Department
Oakridge Resident
Statesman
Popular in the Polls
4th Anniversary
Change Maker
Towloo
Representative
- Joined
- Nov 22, 2023
- Messages
- 360
- Thread Author
- #1
IN THE FEDERAL COURT OF THE COMMONWEALTH OF REDMONT
CIVIL ACTION
HypeGamer231
Plaintiff
V
NotPhunky
Defendant
COMPLAINT
The plaintiff complains against the defendant as follows:
On June 1st, 2024, the plaintiff entered into an original agreement with the defendant (P-001). The agreement was that for $5,000, the plaintiff would demolish the structure on c563. The two parties then later negotiated the original $5,000 price to $15,000 (P-002). All was well until the plaintiff announced that he was going to take a one hour break. At this remark, the defendant told the plaintiff to cease further progress on demolishing despite the fact that the plaintiff and the defendant had already entered into an agreement. The plaintiff is now yet to receive payment and has been prevented from being able to continue progress (P-003).
I. PARTIES
1) HypeGamer231 (Plaintiff)
2) NotPhunky (Defendant)
II. FACTS
1) The plaintiff and defendant entered into an original agreement for the plaintiff to demolish the structure on c563 for $5,000
2) The plaintiff and defendant then negotiated this price to $15,000 for the same amount of work
3) After making progress (P-004), the defendant requested the plaintiff to stop despite the agreement
4) The defendant removed the plaintiff from the plot, preventing him from making progress
5) The defendant hasn’t paid the plaintiff for his work, nor the work that the plaintiff was unable to do due to the defendant’s deliberate actions
III. CLAIMS FOR RELIEF
1) The plaintiff fulfilled their obligations under an agreement with the defendant to the best of their ability. However, the defendant then took steps to prevent the plaintiff from completing the agreement, even though the terms had already been mutually agreed upon. Since the plaintiff upheld their end of the contract before being obstructed, they are entitled to the agreed-upon payment for the work they completed and the work that they were prevented from completing.
2) Taking steps to stop a contract from happening in order to void payment for it is outrageous conduct, and the plaintiff should be entitled to punitive damages for the defendant’s actions.
IV. PRAYERS FOR RELIEF
1) $15,000 in compensatory damages
2) $10,000 in punitive damages
3) $7,500 in legal fees
V. EVIDENCE
P-001
P-002
P-003
P-004
P-005
CIVIL ACTION
HypeGamer231
Plaintiff
V
NotPhunky
Defendant
COMPLAINT
The plaintiff complains against the defendant as follows:
On June 1st, 2024, the plaintiff entered into an original agreement with the defendant (P-001). The agreement was that for $5,000, the plaintiff would demolish the structure on c563. The two parties then later negotiated the original $5,000 price to $15,000 (P-002). All was well until the plaintiff announced that he was going to take a one hour break. At this remark, the defendant told the plaintiff to cease further progress on demolishing despite the fact that the plaintiff and the defendant had already entered into an agreement. The plaintiff is now yet to receive payment and has been prevented from being able to continue progress (P-003).
I. PARTIES
1) HypeGamer231 (Plaintiff)
2) NotPhunky (Defendant)
II. FACTS
1) The plaintiff and defendant entered into an original agreement for the plaintiff to demolish the structure on c563 for $5,000
2) The plaintiff and defendant then negotiated this price to $15,000 for the same amount of work
3) After making progress (P-004), the defendant requested the plaintiff to stop despite the agreement
4) The defendant removed the plaintiff from the plot, preventing him from making progress
5) The defendant hasn’t paid the plaintiff for his work, nor the work that the plaintiff was unable to do due to the defendant’s deliberate actions
III. CLAIMS FOR RELIEF
1) The plaintiff fulfilled their obligations under an agreement with the defendant to the best of their ability. However, the defendant then took steps to prevent the plaintiff from completing the agreement, even though the terms had already been mutually agreed upon. Since the plaintiff upheld their end of the contract before being obstructed, they are entitled to the agreed-upon payment for the work they completed and the work that they were prevented from completing.
2) Taking steps to stop a contract from happening in order to void payment for it is outrageous conduct, and the plaintiff should be entitled to punitive damages for the defendant’s actions.
IV. PRAYERS FOR RELIEF
1) $15,000 in compensatory damages
2) $10,000 in punitive damages
3) $7,500 in legal fees
V. EVIDENCE
P-001
P-002
P-003
P-004
P-005